Week

Date

 
     

1

   

2

   

3

22/5

 

4

29/5

 

5

5/6

Completed PGM design – Begin coding PGM Z13 Presentation

6

12/6

PGM Coding Completed – Completed PGM Testing spec document

7

19/6

Adam away Completed GRA design – Begin coding end of week

8

26/6

Completed GRA coding

9

3/7

Completed GRA Testing spec – Progress on PGM tests

10

10/7

Julian away, Annalisa away Completed PGM Tests

11

17/7

Julian away Completed GRA Tests – Research into Watercasting – Completed Test spec for Mobile testing (inc. equip setup)

12

24/7

Completed Mobile testing – Coding for Watercast as necessary – Completed Watercast Testing spec

13

31/7

Completed Watercast code – PGM, GRA, Mobile research, design, implementation, testing document integration

STOP Coding – concentrate on reports

14

7/8

Rough draft of report – Completed Watercast testing.

15

14/8

Core draft of report

16

21/8

Group work should be COMPLETE

17

28/8

Personal work ONLY

18

4/9

Submit all reports at beginning of week (4/9)

19

11/9

Orals (11/9)